农村黑臭水体治理工程投资估算及经济指标分析

Investment estimation and economic index analysis of black and odorous water body treatment project in rural areas

  • 摘要: 农村黑臭水体治理直接关系到农村人居环境的改善和生态文明建设的推进,合理确定农村黑臭水体治理工程造价指标和投资估算,不仅是推动农村环境综合治理的重要支撑,也是实现精细化项目管理的有效路径。通过X市10个农村黑臭水体治理试点项目的实施方案投资估算与初步设计概算对比,探讨了治理工程的主要造价经济指标及其影响因素。结果表明:农村黑臭水体治理工程因污染源类型多样且分布分散、治理措施复杂,前期实施方案投资估算与初步设计概算之间会有较大差异,造成这一差异的主要原因包括前期实施方案阶段设计深度不足、工程量估算精度不高以及各子项目在技术标准和具体实施措施上的差异性。为提高投资估算的准确性,建议加强前期规划设计,明确治理范围、内容及主要工程量,细化设计方案,完善主要造价经济指标,确保投资估算精度满足要求。本研究基于初步设计概算测算的主要分部分项工程的造价经济指标,可为类似项目的前期投资控制提供决策依据,为农村水环境治理提供实践参考。

     

    Abstract: The remediation of black and odorous water bodies in rural areas is directly related to the improvement of the rural living environment and the advancement of ecological civilization. Reasonably determining the cost indicators and investment estimates for rural black and odorous water body remediation projects is not only an important support for promoting comprehensive rural environmental management but also an effective pathway to achieving refined project management. By comparing the investment estimates in the implementation plans with the preliminary design budgets of 10 pilot projects for rural black and odorous water body remediation in City X, the main economic indicators of remediation projects and their influencing factors were explored. The results indicated that due to the diverse types and dispersed distribution of pollution sources, as well as the complexity of remediation measures, there was a significant discrepancy between the initial investment estimates and the preliminary design budgets. The primary reasons for this discrepancy included insufficient depth in early-stage design, low accuracy in estimating project quantities, and differences in technical standards and specific implementation measures across sub-projects. To improve the accuracy of investment estimates, it was recommended to strengthen early-stage planning and design, clearly define the remediation scope, content, and major project quantities, refine the design schemes, and improve key cost economic indicators to ensure that the investment estimation accuracy should meet the required standards. The economic indicators of major sub-item projects calculated based on the preliminary design budgets can provide a decision-making basis for early-stage investment control in similar projects and serve as a practical reference for rural water environment remediation.

     

/

返回文章
返回